Complex Equipment Remanufacturing Schedule Management Based on Multi-Layer Graphic Evaluation and Review Technique Network and Critical Chain Method
Xingyue Zhang, Wenjie Liu
Nanjing University of Aeronautics and Astronautics
阅读操作
确认中在文库中上传 PDF 后可生成中文音频讲解。
摘要与影响
In order to solve project schedule delays caused by resource conflicts and uncertainty of the environment, work duration, and logical relationship, this paper proposed CCPSP (critical chain project scheduling problem) optimal scheduling model which integrates CCM (critical chain method) and multi-level GERT (graphical evaluation and review technique) network. DEACA (differential evolution ant colony algorithm) is designed to solve the problem, in which DE (differential evolution algorithm) is used to deal with the cross problem and mutation problem, and ACA (ant colony algorithm) is used to deal with each stage of the optimization process. The neighborhood structure is introduced to reduce the invalid search. By storing the non-dominated Pareto optimal solution in external files, the Pareto optimal frontier is obtained. This paper makes full use of the advantages of the two algorithms to achieve fast convergence and a global search for optimal solutions. At the same time of seeking the optimization algorithm, considering the multi-resource constraints, environmental uncertainties and other factors of the project, a buffer is set up, and a “minimum duration - maximum robustness” project schedule is formulated. Finally, through the analysis and verification of the project example, it shows that the project schedule made by this method is feasible.
逐年被引趋势
关键指标
同类平均 = 1
同领域 · 同年份 · 同类型
Google Scholar 与 OpenAlex 的被引统计范围不同,数值存在差异属正常。
AI 辅助阅读
依据:摘要
可就本文提问;依据不足时会说明。
学术脉络
学科主题
计算机 / AIResource-Constrained Project Scheduling
Construction Project Management and Performance · Reliability and Maintenance Optimization
参考文献 9
此处列出前 3 条
引用本文 7
按被引量排序,此处列出前 3 条