Application of a Technique for Research and Development Program Evaluation
D. G. Malcolm, John H. Roseboom, Charles E. Clark, W. Fazar
Booz Allen Hamilton (United States) United States Department of the Navy
阅读操作
确认中在文库中上传 PDF 后可生成中文音频讲解。
摘要与影响
This paper describes the development and application of a technique for measuring and controlling development progress for the Polaris Fleet Ballistic Missile program, Special Projects Office, Bureau of Ordnance, U.S. Navy. Project PERT (Program Evaluation Research Task) was set up to develop, test, and implement a methodology for providing management with integrated and quantitative evaluation of (a) progress to date and the outlook for accomplishing the objectives of the FBM program, (b) validity of established plans and schedules for accomplishing the program objectives, and (c) effects of changes proposed in established plans. In the PERT model, the R and D program is characterized as a network of interrelated events to be achieved in proper ordered sequence. Basic data for the analysis consists of elapsed time estimates for activities which connect dependent events in the network. The time estimates are obtained from responsible technical persons and are subsequently expressed in probability terms. This model is described. Test of the model on a specific component, design of a management control system properly related to existing management systems, reduction to the NORC computer, difficulties in implementation and preliminary results to date are discussed. Limitations of the model, and possible refinements and use of the computer model for testing schedules and for management experimentation in resource and performance tradeoffs are described.
逐年被引趋势
关键指标
同类平均 = 1
同领域 · 同年份 · 同类型
Google Scholar 与 OpenAlex 的被引统计范围不同,数值存在差异属正常。
AI 辅助阅读
依据:摘要
可就本文提问;依据不足时会说明。
学术脉络
学科主题
工程Technology Assessment and Management
参考文献 0
引用本文 931
按被引量排序,此处列出前 3 条