Selection and Weight Determination of Factors for Price Adjustment Formulae Based on Bill of Quantities
Rui Oliveira, María Isabel Abreu, Jorge Pedro Lopes
Universidade Politécnica de Bragança
阅读操作
确认中在文库中上传 PDF 后可生成中文音频讲解。
摘要与影响
This study investigates the effectiveness of standard price adjustment formulae for construction contracts in Portugal. Price adjustment is a mechanism that aims to adjust contractual values to market price fluctuations in labor, materials, and equipment. Such formulae are often generalized and applied in contractual practices without being properly tailored to the specific characteristics of each project. To fill this gap, this study, informed by convergent proposals, builds on the argument that the use of different bill of quantities (BOQs)-based price adjustment formulae for the same contract is fairer, more equitable, and with greater capacity to cushion sudden variations in prices. Using a case study, consisting of a public construction contract, the study analyses price differences obtained through the application of the standard formula and compares them, over different periods, with those obtained through the use of two alternative calculation formulae specifically developed according to the project’s characteristics. The performance of all scenarios was evaluated against the evolution of the growth rate of the construction cost index (CCI). The results demonstrate that the standard formula, even when it is readjusted, provides disproportionate results. In contrast, the BOQ-based price adjustment formulae, developed according to different phases of the works, provide results that are very close to those obtained by CCI-based escalation. The behavior of these customized formulae, even during periods of high price indices increases, closely tracks that of inflation. The results of the study call for the enactment of a more comprehensive legal mechanism so that all cost elements of a construction project can be properly reflected in price adjustment methodologies.
逐年被引趋势
暂无年度引用数据
关键指标
同类平均 = 1
同领域 · 同年份 · 同类型
Google Scholar 与 OpenAlex 的被引统计范围不同,数值存在差异属正常。
AI 辅助阅读
依据:摘要
可就本文提问;依据不足时会说明。
学术脉络
学科主题
计算机 / AIConstruction Project Management and Performance
Public Procurement and Policy · Public-Private Partnership Projects
参考文献 35
此处列出前 3 条